You are working on a project that is scheduled to be completed in 2 years. The total budget for the project is $5,000. Eighteen months have passed and the schedule indicates that 75% of the work should be completed by now. But your team has already completed 90% of the project and spent $3000. What is the Planned Value (PV) for this project at this point in time?
|
|||
|