Use the included spreadsheet (use average production rate) to create a precedence diagram of the following: If the move in activity was delayed by 5 days, determine the number of workers for each activity such that the project will finish on time. Note that you cannot increase the number of workers for asphalt paving and finishing the base as these require specialized equipment. Also, try to minimize the total number of worker days as this will directly affect your profit.