Consider the (simplified) list of activities and predecessors that are involved in building a house, as listed in the table below: (a) Draw a project network diagram. (You may use either Activity on Arrow (AOA) or Activity on Node (AON) for this part) (b) What is the critical path? (Please state clearly which activities are on the critical path.) (c) What is the total project completion time?